welcome

Cotswold

Site

Cotswold Water Park


Client

 Hoburne Ltd


Project

  Café/Bar/Restaurant fit-out


Value

  £550K


Duration

  14 weeks


Working closely with architects NBDA and interior designers VK Works this 12 week Café, Lounge Bar and restaurant refurbishment was undertaken for Hoburn Holidays. This project included asbestos removal, major structural alterations and drainage works to achieve the designer’s layout.

Not unusual for this type of project many unforeseen issues arose when altering the structure but WCR responded rapidly to those issues and works completed two weeks early.