WCR Construction Limited
contact us
WCR Construction Limited
welcome

Cineworld Harlow

Site

Cineworld Harlow Harvey Centre


Client

 Cineworld Plc


Project

New 6 screen cinema fit out


Value

  £1.8m


Duration

15 weeks


Following extensive remodelling and refurbishment of the harvey centre shopping centre by the landlord.

WCR commenced a new fit-out of a 6 screen cinema to a 1st floor unit formerly occupied by Tesco. An initial construction period of 18 weeks was originally envisaged by Cineworld, but WCR offered a construction period of 15 weeks to enable the cinema to open in time for Star Wars Rogue One . During the construction period the shopping centre was fully operational so works were closely co-coordinated with the Centre Management and other retail tenants and completed on time and within budget.